ISKOPANO PRVIH 100 METARA TUNELA VIJENAC

FIRST 100-METRE MILESTONE IN VIJENAC TUNNEL

The excavation of Vijenac tunnel has reached the first 100-metre milestone. The works are proceeding according to schedule, and the excavation is expected to continue at the same pace. The estimated daily progress for the current soil category is 1.5 metres, but our company is drilling two metres per day. Below you may find the latest photo updates from this construction site.