IZGRADNJA TUNELA VIJENAC

VIJENAC TUNNEL CONSTRUCTION

78.8 metres of the top heading of Vijenac tunnel have been excavated so far. Presently the drilling is proceeding through the C3 soil category. The bench excavation is proceeding according to plan and the top-heading-and-bench technique.

Workers have also completed one segment of the invert arch with sprayed concrete, and have finished the excavation and reinforcement of the cutting approach. They also continued with the arranging of the building site. The project is proceeding according to schedule.