SUHODOL-TARČIN MOTORWAY CONSTRUCTION UPDATE
The presently ongoing construction works on the 5c Corridor motorway section Suhodol-Tarčin include the clearing of shrubs and trees of up to 10 centimetres in diameter, cutting of trees with trunks between 31 and 50 centimetres in diameter, excavation of the surface soil along the entire course of the motorway as well as the slip road B, filling of rock aggregates for the booster pump service road, filling of profile embankments and cutting of the booster pump road, excavation of Tarčin junction right side underpass, surface cutting for the cross-section 305 culvert with a gravel embankment and a concrete subbase, surface cutting for hydraulic structures, setting of rebars, removal of surface soil, and pouring of concrete.
Other works include the redirection of Kalašnica and Košuta brooks. Below you may find helicopter views of the construction site.