RADOVI NA IZGRADNJI GGM ZENICA

GGM ZENICA CONSTRUCTION UPDATE

The following construction works on the Primary Urban Thoroughfare in Zenica have been under way in June: relocation of underground utility installations at Bojin Vir, completion of all construction on Metalurg roundabout except for the installation of light poles, paving of footways and kerbs along the entire repaved length of Asko Borić St, pavement milling and subbase replacement in Goražde St, construction of new manholes for the relocation of underground utility installation at roundabouts Drveni Most and Crkvice, raising of support scaffolding between piers 1 and 2 of the M1 Bridge, expansion of piers 1 and 2 of the Lukovo Polje Bridge, and waterproofing of the Kočeva Bridge.

The project is proceeding according to schedule. Below you may find the latest photo updates of this project.