KRAVICE-BIJAČA MOTORWAY CONSTRUCTION, JANUARY UPDATE
The construction of the Kravice-Bijača motorway is proceeding according to schedule. The current tasks include the construction of embankments, construction of concrete abutments for the Sulet and Galići underpasses, pouring of concrete foundations for motorway control and maintenance centre, installation of water pipes, and preparations for the subbase filling.
Preparations are also under way for the construction of drainage systems and concrete cable ducts. The construction of a 2,000 mm culvert and the excavation of the Dol underpass have been completed. Below you may find the latest photo updates of this construction site.