KRAVICE-BIJAČA MOTORWAY DECEMBER UPDATE

When it comes to the construction of Kravice-Bijača motorway section, in December the project focused on the filling of embankments with a daily average of more than 8,000 cubic metres of rock aggregates, as well as the construction of a 2,000 mm culvert, and the underpasses Supet and Galići.

Apart from these activities, workers are also proceeding with the relocation of pipelines. The project is progressing according to schedule.