IZGRADNJA TUNELA VIJENAC

VIJENAC TUNNEL CONSTRUCTION

As part of the construction works on the northern side of the Vijenac tunnel’s right tube, as of the 12th of April 2012, Euro-Asfalt has excavated 520.6 metres of the top-heading, 365 metres of the bench, 240 metres of foundations on the right side, and 180 metres of foundations on the left side. Works are also proceeding on the excavations of the invert arch, which has so far reached the 168-metre line. The excavation of the 2.8-metre pedestrian cross-passage between the tunnel tubes has also commenced. Below you may find the latest photo updates from this construction site.