BUSINESS MAGAZINE EURO MANAGER INTERVIEWS TOP MANAGER The Chief Executive Officer of Euro-Asfalt Sarajevo, Hamed Ramić, has been awarded the title of Top Manager in Bosnia and Herzegovina, and deservedly so. At the same time, Euro-Asfalt has once more been declared the top company in the category of construction industry – Euro Manager. Below you…
SIGNING CEREMONY FOR VLAKOVO-LEPENICA CONSTRUCTION AGREEMENT Turkish company Cengiz Insaat will be tasked to construct another 10.1 kilometres of motorways in Bosnia and Herzegovina between Vlakovo and Lepenica. This way the company will be in charge of the entire 20-kilometre Vlakovo-Tarčin section, which is already under construction and should be opened by the autumn of…
EURO-ASFALT TAKES PART IN JOBS FAIR Our company took part in the Jobs Fair, which is traditionally organized by the Employment Bureau in partnership with Posao.ba. The aim of this fair is to gather employers in one place to present their job openings, and to introduce companies to potential employees. Euro-Asfalt has encountered an excellent…
AUDIENCE WITH DEPUTY RULER OF DUBAI On Friday, the 14th of December, a delegation of BBI Bank, BBI Real Estate and Euro-Asfalt – members of the BBI VIP Business Club –had an audience with the Deputy Ruler of Dubai and the United Arab Emirates Finance Minister, Sheikh Hamdan bin Rashid Al Maktoum. During the audience,…
ZENICA PRIMARY URBAN THOROUGHFARE CONSTRUCTION UPDATE Construction works on the Primary Urban Thoroughfare in Zenica are proceeding with the preparation of the thoroughfare course, including the preparation of subgrade for Bojin Vir roundabout, construction of retaining walls along the main course, and paving of access roads for the M1 Bridge. The paving of the M1…
SUHODOL-TARČIN MOTORWAY CONSTRUCTION UPDATE Construction works on the 5c Corridor motorway section Suhodol-Tarčin are proceeding according to schedule. The earthworks have been completed, and currently the work is advancing on the motorway bed. The construction of RC structures is also under way – a bridge over Kalašnica River, one underpass, and four culverts. As for…
VIJENAC TUNNEL CONSTRUCTION UPDATE Euro-Asfalt is in charge of construction works on the southern side of both tubes of the Vijenac tunnel. The tunnel is part of the 5c Corridor motorway. The excavation of the top heading in the left tube has reached 1,522.20 metres, the bench 1,166 metres, the base 840 metres, and the…
KRAVICE-BIJAČA MOTORWAY CONSTRUCTION UPDATE The construction works of the 5c Corridor motorway section Kravice-Bijača are currently focused on the drainage system, cutting, embankment construction and subbase filling, surface water runoff management, construction of kerbs, kerb outlets and paving, pouring of concrete foundations for lamp posts, construction of the protective fence, assembling of support scaffolding for…
SUHODOL-TARČIN MOTORWAY CONSTRUCTION UPDATE The presently ongoing construction works on the 5c Corridor motorway section Suhodol-Tarčin include the clearing of shrubs and trees of up to 10 centimetres in diameter, cutting of trees with trunks between 31 and 50 centimetres in diameter, excavation of the surface soil along the entire course of the motorway as…
R-445 – ILIJAŠ ROAD RECONSTRUCTION UPDATE In the past weeks, Euro-Asfalt has been in charge of the reconstruction of R-445 road through Ilijaš. The project is proceeding according to schedule. Following the completion of preparation works, the workers moved on to paving the 1,100-metre road section stretching from the Orthodox Church to the grade crossing,…