MIHRIVODE HOUSING DEVELOPMENT
Works are continuing on the housing complex Mihrivode, which consists of three units, together with accessories and utilities. Construction works on Unit 1 are currently focusing on the erection of walls between sections 300 and 400, as well as the drilling of reinforced concrete slabs for plumbing installations. Workers in Unit 2 are erecting shutters for the pouring of reinforced concrete slabs at section 200. As for Unit 3, workers are currently erecting shutters for concrete slabs at section 300, and building separation walls in the basement.
CONSTRUCTION OF DRIVUŠA-GORICA MOTORWAY
Construction of the 5c Corridor motorway section between Drivuša and Gorica is currently focused on filling the embankments with rock aggregates, backing up the retaining walls with crushed stone, and erection of shutters for the building of retaining walls.
Other activities include filling and construction of the culvert inlet at chainage point 3+318, as well as the construction of electrical concrete manholes.