RADOVI NA IZGRADNJI TUNELA VIJENAC

VIJENAC TUNNEL CONSTRUCTION UPDATE

The construction tasks Euro-Asfalt is in charge for are progressing according to schedule. As of the 31st of May, 2012, excavations and primary formwork setting have reached 723.4 metres for the top heading, 467 metres for the left-side bench, and 469 metres of the right-side bench. Excavation of foundations is also under way, reaching 396 metres on the right side and 348 metres on the left side.

The excavation of the left-side invert arch has reached 336 metres, and the right-side 372 metres. 16.1 metres of the pedestrian cross-passage between the tubes has been built so far. Below you may find the latest photo updates from the construction site.